Accept Completion of Citywide Road Repair Phase IX; Release Retention to Hardy & Harper ($257,113.58)
This item closes out a completed road repair project in your city, releasing final payment to the contractor after confirming the work on Compton streets meets city standards.
Jul 14, 2026
Accept Completion of Citywide Road Repair Phase IX; Release Retention to Hardy & Harper ($257,113.58)
This item finalizes road repairs on dozens of streets across Compton — including new pavement, speed humps, and striping — so you can drive, walk, and bike more safely in your neighborhood.
Jul 14, 2026
Fire Station Driveways Project Notice of Completion
These improvements ensure fire trucks can quickly respond to emergencies in your neighborhood without delays from damaged station driveways.
Mar 11, 2025
Artesia Boulevard Bridge Project Notice of Completion
This completes the critical bridge repairs on Artesia Boulevard that keep this major east-west route open for your daily commute.
Mar 11, 2025
Acceptance of Citywide Road Repair Services VII Project
This officially completes street repairs on 20 roads throughout your city - smoother streets mean better driving conditions and reduced vehicle damage from potholes.
Dec 10, 2024
Accept Completion of Street Rehabilitation Project Phase 2B
This formally accepts completed street improvements on Compton Avenue, Slater Avenue, Rosecrans Avenue, Santa Fe Avenue, and 133rd Street that provide better roads for your daily driving.
May 7, 2024
Completion and Retention Release for Citywide Pothole Repair Project
Your streets will be safer and in better condition as this pothole repair project is completed, reducing hazards for drivers and pedestrians in your neighborhood.
Jan 7, 2020
Well No. 20 Water Treatment Plant Project Completion
Your city's water infrastructure is being improved to help ensure clean and reliable drinking water for you and your family.
Apr 17, 2019
Accept Street Rehabilitation Project CDBG #13-02 as Complete
Your streets in CDBG areas have been rehabilitated with improved pavement, curbs, sidewalks, and handicap ramps for safer passage.
Jun 21, 2016
Traffic Management Operations Center Project Completion
This advanced traffic management system at 48 signalized intersections will help improve traffic flow and safety on your streets throughout the city.
Jan 19, 2016
Accept Williams Alley Paving Project Construction Completion
The alley between McMillan and Rosecrans on Williams Avenue is now paved, eliminating the public nuisance and maintenance problems that affected residents in the area.
Jul 22, 2014
Resolution 23,890: Well #20 Project Completion and Retention Release
Your water infrastructure at Sibrie Park will be improved with the completion of this new well.
Dec 17, 2013
Resolution - Notice of Completion for Well #20 at Sibrie Park Construction
The city completes well construction at a park, ensuring your access to water infrastructure and park facilities.
Dec 17, 2013
Notice of Completion for Water Storage Reservoir Construction in Sibrie Park
This water storage facility improves your community's water supply reliability and capacity during peak demand or emergency situations.
Nov 12, 2013
Resolution 23,861 Authorizing Notice of Completion for Water Storage Reservoir
Your city completes a water storage project that improves water supply and infrastructure in Sibrie Park.
Nov 12, 2013
Accept Greenleaf Corridor Improvement Project Completion
Your neighborhood park improvements at the Walton and Mayo sites are now complete with new walkways, landscaping, exercise equipment, and safety features that your family can enjoy.
Feb 14, 2012
Hardy & Harper, Inc.
$257KRelease of retention funds to Hardy & Harper, Inc. upon completion of Citywide Road Repair Services Project Phase IX
Hardy & Harper, Inc.
$257KRelease of 5% retention funds withheld from progress payments to Hardy & Harper, Inc. upon project completion
Hardy & Harper, Inc.
$103KRelease of contractor's retention funds
Accept City-Wide Pothole Repair Project as Complete
$32KRelease of contractor's retention funds for pothole repair project